The Talent Crucible
Workforce Risk Analysis for U.S. Gulf Coast LNG Export Infrastructure
Report Type
Executive White Paper
Date Published
February 2026
Authors
Luke Marshall & Rodrigo Sandoval, PhD
Executive Summary
The U.S. Gulf Coast faces a structural workforce shortage that poses material execution risk to the current wave of LNG export infrastructure development. This analysis quantifies the magnitude of the challenge and identifies strategic workforce approaches that differentiate projects positioned for on-schedule delivery from those at elevated risk of cost escalation and delay.
Key Findings
- •Scale of Demand: Approved LNG projects represent approximately $80 billion in capital investment, with combined peak construction workforce requirements of 45,000-51,000 workers.
- •Critical Convergence: Peak regional demand will occur in late 2026 through early 2027, when multiple megaprojects reach maximum staffing simultaneously.
- •Regional Capacity Gap: Lake Charles requires 209% growth; Monroe requires 369% growth in workforce capacity.
- •Demonstrated Impact: Labour constraints contributed to multi-billion-dollar overruns, with Golden Pass LNG experiencing $2.4 billion in cost escalation.
- •Structural Constraints: Demographic retirements (29% by 2026), constrained immigration, and multi-year training timelines limit mitigation approaches.
Strategic Implications
Projects that treat workforce planning as critical infrastructure—deploying direct-hire or hybrid labour models, structured retention programmes, modular execution strategies, and early commissioning integration—will be positioned to capture value in the 2026-2028 execution window.
Projects that approach labour as a transactional procurement function face elevated probability of schedule delays, cost overruns, and diminished returns on invested capital.